The week of Sept 30th

In the last week the first components of the WFU went into place. We are currently right on schedule.

This week we will be clearing out the last components at the top of the tracker, finishing the removal of any old interconnects on the ground and prepping the dome floor for the next big crane lifts in the following week.

Also we will have painters out at the HET site repainting the CCAS tower white and painting the side of the tower that faces the mirror flat black. Hopefully someone will have some before and after shots of this work.