The week of October 2nd

This week we are pleased to announce that a new VIRUS unit was installed in side two of the VIRUS enclosure. This brings us to 22 VIRUS units or 44 spectrographs. We also took a little time in the last engineering run to add on some valves to the vacuum fittings which will allow us to cold pump on the VIRUS units which takes far less time to do than to warm up and then repump which was our older methodology. Keeping 22 VIRUS units going is starting to be a little easier but still takes a lot of management.

In addition to the work on VIRUS, we have also installed in the coherent fiber bundles for the HPF. These coherent fiber bundles will be used to setup stars on HPF science fibers. HPF will arrive in the coming weeks and we are very excited to get our first high resolution instrument on sky in the coming months.