Last week we finished up the metrology measurements of the upper hex and all of the cableways in the lower electrical room and spectrograph room.
This week we will have welders on site working on the channels for the lower X stiffener and also the new work platform for the outside of lower X. We are also taking apart the MRS enclosure for storage, reshelving the Az cable wrap and installing static cable wrap. We continue to be on schedule.