Monthly Archives: December 2015

The week of Dec 7

Two weeks ago was the HET Board of Director’s meeting in Penn State. The meeting lasted two days and the Board got status reports from HET operations and each of the instrument teams. The main news is that that LRS2 is expecting to reach first science in the first few months of 2016, HRS2 is going to start commissioning before Summer 2016 and VIRUS units are going to be coming in over the next 9 months. The Board was encouraged by the progress being made and hopes that we can continue the pace. They were also pleased to see the progress being made on HPF and were impressed with the clean room facility tour they were given. No major changes or action items were reported by the Board.

Once the commissioning team returned from Happy Valley, we went right back to work and were able to push along the closure of one of our major metrology loops, the guide probes. I am pleased to report that we are able to guide at any telescope Az for full trajectories with the probes at any position within their range.