The week of September 4th

We have now observed one month out of four in the 2017-3 period. The month started off pretty slow with lots of bad weather in August but we have had some good clear nights. We are still conducting 7 days of engineering around full moon, at least until we get our first bright time instrument. So far we have collected 52.9 hours of charged time and completed 21.8% of the TAC allocated time. We have started collecting the first LRS2 Guaranteed Time Observations (GTO) allocated by the HET board for the instrument team as well as the first time allocated by the HET board for the HETDEX experiment. The latter includes time on well studied fields to make sure that our Lyman alpha emitters detected not really other types of emission sources and to better quantify our sensitivity/throughput.