Author Archives: shetrone

The week of December 9

Last week the electrical team finished straight pieces for the cable runs up the side of the telescope and have to purchase the transition curved pieces to finish the cableways. Weathers Electric started work on the improvements we require for the new tracker. This is likely to take 4-6 weeks but they made some progress outside with the conduit. Veliez construction was on site over the weekend cutting concrete paths for the glycol, liquid nitrogen, power etc.. They finished their concrete cuts. We had our Board of Directors meeting this past weekend and they had a chance to see all of our progress in the Wide Field Upgrade. The next board meeting will be in June also out at McDonald so that they can see the completed Wide Field Upgrade.

This week we will be finishing the weldments and then painting them. Weathers electric will continue work on site, mostly on the outside conduit. Veliez construction will be back on site later in the week to jack-hammer out the concrete cuts and then line and level the trenches. They hope to finish that effort this next weekend.

The week of Dec 2

In the past week we had a very significant power outage caused by a large snow/ice storm. The outage lasted from Saturday Nov 23 until Tuesday Nov 26. The next day was spent getting all of our subsystems back up and checked. Thankfully no permanent damage was found to the facility but this has put us about 3 days behind schedule for all activities.

Since the last blog posting we have gotten a start on a number of projects high up on the tracker including: mounting the lower X work platform and handrails, modification of the lower and upper X screw weldments, welding on the lower X cable tray brackets, positioning of the lower and upper X screw mount weldments.

This week we will be welding on the upper hex weldments and installing the DAS-box weldments. When the JLG manlift is not in use by the welding team the electrical team will be installing the cable trays up the side of the structure or rearranging the azimuth cable wrap.

We also have Weathers Electric and Veliz Construction on site setting up power to the lower electrical room and cutting slots in the dome floor for the additional glycol, power, nitrogen and liquid nitrogen lines.

A very busy week….. Just in time for our Board of Directors meeting this weekend.

The week of Nov 18

Last week the certified welders finished up work on the X-rail stiffener and the supports for the lower X work platform. Logan was able to strip the M4 witness sample with a fairly simple Greenriver solution.

This week we will have our local welders finish up with the tracker weldments. We will also be working on the cable trays that lead from the cable wrap up the telescope structure toward the tracker.

M4 in Corrector will need to be recoated

While working on the alignment of the corrector at UA, out team found that the coating on M4 (and a few of the witness samples that came with it) was beginning to have signs of coating failure, bubbling and spotting. Our current plan is to send the witness samples to McDonald so that we can confirm the stripping process for this very tough coating and then send that witness back to UA so that they can confirm that the witness has not been damaged. Meanwhile UA will continue to work on the corrector alignment with M4. If all goes well we will then strip the coating from M4 and send it to be recoated once they have all alignment issues worked out. The question remains about who will do the recoating.

We hope to act quickly and get M4 back to UA for final alignment before shipping to McDonald in the spring.

So far this does not pose an imminent threat to the WFU schedule.

The week of Nov 11

Last week we finished up the metrology measurements of the upper hex and all of the cableways in the lower electrical room and spectrograph room.

This week we will have welders on site working on the channels for the lower X stiffener and also the new work platform for the outside of lower X. We are also taking apart the MRS enclosure for storage, reshelving the Az cable wrap and installing static cable wrap. We continue to be on schedule.

The week of Nov 4

In the past week we finished cleaning up the upper hex. In the process we had to move some of the cameras around in our internal views of the dome so the view located at:

http://het.as.utexas.edu/wfu might look a bit strange until we get around to moving the cameras back into place.

This week we will be starting the metrology of the upper hex in preparation for putting on the upper and lower X rails. This metrology is done with a laser tracker and small “nest” mirrors placed around the telescope structure. Other activities this week will include finishing up the cable-ways in the lower electrical room and spectrograph room, work on the structure azimuth cable wrap, and work on the static cable ways. It is amazing the amount of power wires, optical cables, glycol and air lines that need to be strung up.

We are still right on schedule.

The week of Oct 28

In the past week we finished most of the work on the Virus Support Structure (VSS) and on Friday were able to have the first rotation including the new air bearings under the VSS. In addition, we had some of the team working on sealing the dome enclosure. Vicki worked on the outer vents at the base of the ring wall and Logan and Kathryn worked on the dome and sealed the nodes near top.

DomeNodes1

This week we will be finishing the clean up of the upper hex removing the trollies, encoders and last of the interconnects. We will also make room for the new JLG man-lift (we call Jr.) on the dome floor. This work is in preparation for the work that John Good will start in Nov.

The week of Oct 21

This past week we worked on getting the Virus Support Structure (VSS) cross supports and over-turn preventers welded into place. Other activities included test digs around the location of the liquid nitrogen tank and the vault for the remote thermal area, setting up the air system for the VSS and continued work on the cable-ways for the lower electrical room.

This next week we should finish the VSS work which means that we should be able to unlock structure rotation. If all goes well we will now have the Structure firmly welded to the VSS and they should rotate together as if they were one system.

The week of Oct 14

In the past week we had great guys from Crane Services out to the HET to remove the old tracker bridge from the dome, move the new lower X and upper X assemblies onto the dome floor, and move the VSS into place. It all went very smoothly and they finished on Thursday about 1 hour before a small windstorm (by West Texas standards) moved in.

There are numerous pictures taken by:

Jerry Martin

Dave Doss of the Old Tracker lift

Dave Doss of the VSS installation

and here is a picture of the tracker removal taken from Renny Spencer who was purposefully stranded up on the upper X beam to monitor the lift.

310

There is even a movie produced by Eusebio Terrazas:

http://het.as.utexas.edu/wfu/

This next week we will be tuning up the VSS, putting in the diagonal bracing and getting ready to hook it up to the air bearing system. Other work at the HET includes putting in cableways in the lower electrical room and spectrograph room, stripping the old coating from the primary mirror segments that were removed before the upgrade began, and applying extra sealant to the dome nodes.

The week of Oct 7

Last week we finished the painting of the CCAS tower and the removal of the equipment on upper X hex.

This week we will expect a crane to arrive on Monday and from Tuesday through Friday we will be removing the old tracker bridge, install the Virus Support Structure and stage the upper and lower X rail assemblies for the new tracker onto the dome floor. The upper and lower X rail assemblies will be shipped from CEM in Austin to McDonald on Monday so that they will be on site Tuesday morning. The road to the top of the mountain will be closed to non-essential personnel.

We are still on schedule.