Author Archives: shetrone

The week of May 25

This was a big week for us. The Corrector optics and the Focal Plane Assembly arrives this week. Instead of the normal, mostly text blog, I thought I would just post a few pictures showing their arrival.

The Focal Plane Assembly, which will hold all of the guide probes and science fibers, arrives at the HET and is moved into the loading bay and then into the dome.

The Focal Plane Assembly, which will hold all of the guide probes and science fibers, arrives at the HET and is moved into the loading bay and then into the dome.

The Wide Field Corrector on its test stand in Arizona  just before being loaded into the transport box.

The Wide Field Corrector on its test stand in Arizona just before being loaded into the transport box.

The WFC in the transport box coming slowly up the mountain.   It had a police escort and traveled 45 mph all the way from Arizona!

The WFC in the transport box coming slowly up the mountain. It had a police escort and traveled 45 mph all the way from Arizona!

WFC arrives at the HET.   We have to get it off the truck into the loading bay without exceeding the acceleration tolerances.

WFC arrives at the HET. We have to get it off the truck into the loading bay without exceeding the acceleration tolerances.

The experts from Crane Services lift the WFC over to the mouth of the loading bay.  Then our expert sky track driver (seen earlier moving the FPA into the loading bay) moves it the rest of the way.

The experts from Crane Services lift the WFC over to the mouth of the loading bay. Then our expert sky track driver (seen earlier moving the FPA into the loading bay) moves it the rest of the way.

The week of May 11

Much of the work in the last couple of weeks has focussed on the imminent delivery of the wide field corrector from Arizona later this month. We will have to test that the optical alignment of the corrector survived the trip down HWY 10 by placing it in a make shift clean tent put together in the loading bay of the the HET. This tent has two HEPA air conditioning units and a dry nitrogen purge line to keep the optics clean. Although it takes up most of the loading bay we still have just enough room to squeeze around it to allow operations to continue. See the picture below.

A panorama shot of the clean tent being assembled for the delivery of the Wide Field Corrector

A panorama shot of the clean tent being assembled for the delivery of the Wide Field Corrector

Because of the slight delay mentioned in the previous blog post we have been looking at sub-systems which might cause further delays during the commissioning effort. This week we spent several days trying to increase the reliability of the communications in the CCAS tower and to shorten most copper cables and replace them with fiber where possible in advance of lightening season.

The night operations and software development teams continue to make progress on the Telescope Control System. Despite several weeks of delays due to poor weather we can now run trajectories on the sky with the tip-tilt camera and Distance Measuring Interferometer running to make refinements to the mount model of the telescope. We have also exercised the system with a few score of trajectories finding small bugs in the code well in advance of the bulk of the commissioning which will take place when the wide field corrector is mounted on the telescope in June.

In the last few weeks we have had an opening for a telescope operator. If you know of someone with a STEM (Science, Technology, Engineering and Math) background who would be excited by the idea of running one of the largest telescopes in the world and living in the the lovely Davis Mountains be sure to have them apply:
Positions open at McDonald Obs.

The week of April 20.

The big news from this week is that the review of the secondary corrector optics has completed. The review involved people internal and external to McDonald Observatory. The reviewers agreed with the WFU commissioning team that the corrector was ready to be shipped to the HET. However, they firmly suggested that the amount of knowledge transfer from University of Arizona to the maintenance team at the HET was not sufficient. Thus there will be a ~3 week delay in shipping the corrector so that the HET optical maintenance team can travel to University of Arizona and review the alignment procedures for future reference and in case of an unanticipated disaster in bringing the optics to the HET. This means that the corrector will not arrive in early May as planned but will arrive later in May.

The past three weeks have been dedicated to getting the telescope ready for various aspects of the upgrade. The mechanical and electrical teams have been trying to finish out various aspects of the VIRUS enclosures. The HRS has been stripped down to the optics table and the inside of the enclosure painted flat black.

The mirror team continues to pull the oldest mirrors in the array and replace them with freshly coated mirrors.

The night operations team continues to make sure that the alignment software is working well and is able to align all of the mirrors. Some tests of the telescope control system and mount models for the tracker motion have been tested. We now have pointing and tracking capability comparable to what we had before the upgrade began.

In the last few weeks one of our electrical technicians decided to retire. We have decided to change the position from a technician to an engineering position. If you know of an electrical engineer who is interested in living in West Texas be sure to have them apply:
Positions open at McDonald Obs.

The week of March 23

We did some simulations of data transfer rates in preparation for VIRUS coming on line. The data set consists of 900 fits files; each file is 8524800 bytes in size. The working assumption is that one Hetdex image consists of 150 spectrographs x 2 amplifiers/spectrograph x 3 dither per field with a CCD size of 1032×2064 pixels. Total data size is 7,672,320,000 bytes (7.3 GB). The data would be collected over 20 minutes (~6 minutes per dither) but it only took 449.5 seconds (7.5 minutes) to transfer this data to Austin. Thus we should be able to keep up with the data collection rate without bringing the network to a crawl.

The large air and glycol (“Blue Thunder”) hoses were installed through the Az wrap and laid in the trench in the floor and through one of the ports through the pier to the ring wall in the last two weeks. The next step will be to connect these to the outside lines and do a pressure test of the system.

All power connections for the VIRUS enclosures are now complete and tested. We have also conducted some heat load tests on the liquid nitrogen system by placing plastic bags over each of the VIRUS bayonets (the component that will stick into a VIRUS unit to keep it cold). So far most of the system checks out close to specification.

The primary mirror group installed 4 mirrors this week and continue to keep up their 30% over expected swap rate in hopes of being close to completion when the corrector is ready for commissioning.

The CCAS shutter failed this week and could not be repaired from inside the CCAS Dome. Instead of having to rent a very expensive 90 ft manlift the mechanical team found a way to safely undo the mounting to the CCAS Dome and lower it to the ground. A replacement shutter is on order and should arrive in the next week or two. It will be installed by just reversing the procedure developed to remove the old shutter. Until then we’ve installed a simple wood plug that can be removed manually (after climbing the 90ft tower) to continue with critical primary mirror work.

The week of March 9

The grating and guard rail around the liquid nitrogen tank have been completed. This gives the contractors safer access to the controls during our filling.

The air and glycol (“Blue Thunder”) hoses arrived and installation may start as early as next week. This will actually shut down the structure for a day or two as these are carefully integrated into the azimuth cable wrap below the telescope.

The HRS instrumentation team came out from Austin and disassembled the HRS and packed the optics up. Some of the optics will just be stored while the coated optics are being shipped out to be recoated for the HRS upgrade. The HRS enclosure has been cleared and once some preliminary electrical work is done the inside of the enclosure will be painted flat black.

Our telescope operator and video production guru has completed a new video showing the installation of the temporary clean room frame. See http://het.as.utexas.edu/wfu/ This clean room will house the corrector when it arrives in late April.

A visiting engineer from Texas A&M was back this week with the doors and sides for the VIRUS enclosure. A lot of work continues to seal, plumb and install electrical components in the enclosures and annex.

In night time commissioning we attempted a rewind test. This is to measure the time it takes from the abort of one 20 minute trajectory and rewind and start a 2nd trajectory. It took 79 seconds to make this transition which is a little longer than we really wish but still within the 80 seconds from abort to guider acquisition. We hope to shave 9 seconds off this time so that we can have 10 seconds to have the metrology and guiders acquire their stars.

The mirror team has been getting ahead of their minimum swap rate by swapping another 5 mirrors this last week. They hope to have all of the older mirrors swapped out by the time we start re-commissioning the telescope.

The week of February 23

The last two weeks have not seen any obvious large changes to the facility. Some of the team continue to work on the VIRUS enclosures and their annex. The Annex is where much of the breakers, electronics, fans and junction boxes are located. Other members are sealing/caulking the seams of the enclosure so that when we close it up it will be air tight.

We did have some contractors on site finishing up a few punch list items from our remote thermal area project including a team from Trane came out last week to setup some of their communication hardware and test the glycol temperature control system as far as possible without a load on the system.

We painted some test squares of ultra flat black on the High Resolution Spectrograph (HRS) enclosure in preparation for the beginning of its upgrade.

The mirror team has swapped 4 mirror mirrors in the last two weeks keeping on schedule. They continue to make some improvements to the Strip and Wash room including installing a 2nd hot water hose in strip wash area and adding acid proof shelving.

The at angle tests with the wide field corrector at the University of Arizona are going well. So far all deflections detected are elastic and within specification. We are going to have a final review of the corrector alignment with several external experts in early April to get the final ok for shipping the corrector to the telescope.

The week of February 9

This past two weeks have been eventful. Most of the prior week was spent trying to get the VIRUS enclosures and cryogenic safety systems online for the first delivery of liquid nitrogen into our big tank. This involved installing lots of cryogenic lines and one large LN2 tank on each of the VIRUS enclosures.

Screen shot 2015-02-16 at 12.17.03 PM

Although a few last minute alterations had to be made, the filling of the tank went smoothly. A single truck can not fill our tank but we did put in 4,000 gallons of LN2 into it. Much of this liquid would be burned off quickly to cool the tank and all of the cryogenic lines that lie between the tank and the VIRUS enclosures. Just for reference the cost of very pure LN2 trucked out to W. Texas is about a dollar a gallon.

The contractors for the tank and cryo-lines lead a safety class for the staff and we reviewed all of the alarm and oxygen sensors now placed around the facility.

The mirror team continues to swap freshly coated mirrors for the mirrors with the oldest coatings. This past week they swapped 4 mirrors.

We have installed an in-line filter for the fan venting the CCAS tower. This filter will allow us to reverse the fan and run it continuously during the day to keep the tower close to ambient temperature. The software group has finished a prototype piece of code that will turn off the fan just after sunset or if the weather conditions indicate a “close all domes” condition such as high humidity or dust.

The wide field corrector is undergoing extensive “at angle” testing to make sure that the alignment can be maintained between the assembly and shipping vertical axis and the 55 degree angle that it will live at in the tracker. These tests are being done at University of Arizona. When done the corrector will be put into a special shipping box and sent to W. Texas on a special air-ride truck.

Screen shot 2015-02-16 at 1.30.05 PM

The week of January 26

Happy New Year! The blogger is back from Winter break and travels to January Science meetings.

We will start with the bad news. The tests on the corrector have determined that there is significant asymmetries. These are asymmetries beyond what were found and reported to the board of directors in the December meeting. Those aberrations were going to be removed by changing the plate glass that was going in to seal the bottom of the corrector into a fifth optical element with some small power. That optic has been fabricated and installed in the corrector. The newly discovered astigmatism was found off axis and might have an impact on image quality at the edge of the field of view. To further investigate this optical issue we are adding a few months to the delivery date of the corrector. Instead of being delivered in late January the new delivery date is expected to be early May and significant on-sky commissioning during the rainy season perhaps pushing us into September.

On a more positive note the 2nd VIRUS enclosure has arrived and installed.

Panoramic views showing the VIRUS Enclosures being installed.  The top shows a view from in-front of the mirror and the bottom shows a view from behind the mirror.  Both are taken from the catwalk.

Panoramic views showing the VIRUS Enclosures being installed. The top shows a view from in-front of the mirror and the bottom shows a view from behind the mirror. Both are taken from the catwalk.

There is a lot of plumbing and electrical work required to finish the installation. This is our highest priority.

During the long break the Remote Thermal Area contractors have installed the glycol chiller and are in the process of commissioning it with glycol. This nearly completes the Remote Thermal Area project. Only a few punch list items remain.

The HPF doors also arrived and have been installed. The HPF is now thermally isolated from the spectrograph room. The Penn State Team will monitor the temperatures inside and outside of their enclosure to see if our new Mitsubishi units can hold the temperature to a tight enough tolerance for their specifications. Meanwhile the insulating panels for the HRS II have arrived and will be installed in the coming month. These panels along with an active feed back heater inside the enclosure should allow the HRS II to be held to extremely tight tolerances, < 0.1 C.

The mirror team has started mirror swaps and started using the Strip and Wash room to remove old mirror coatings and prep them for the coating chamber. Our goal is to get the team up to 4 mirrors swaps every 3 weeks.

The week of December 15

As mentioned in the previous post in the week of December 8 many of the staff were working off the facility. This week most everyone is back on site.

The team who went to Texas A&M had a very busy week. They soldered glycol lines, installed covers and tested the system under pressure. They found some leaking at 40 psi and at 80 psi the leaks were severe. The team left it back in the hands of the A&M engineers for them to fix these severe problems. The 2nd VIRUS enclosure is supposed to go on the telescope in January and at that time we would like to do an end to end test of the chilled glycol system.

The team who went to Germany for the HET board of directors meeting brought back good news. The board was pleased to see the progress that the operations team is making and authorized the use of some operations funds for the wide field upgrade to make sure that the teams in Austin and West Texas have enough personnel to stay on schedule for a summer time first light. They were also impressed with the latest installation video, the nitrogen tank installation. Please have a look at: https://www.youtube.com/watch?feature=player_embedded&v=2a1xZF1b0wQ.

The groups that were not traveling have been busy as well. The work on the Anemometer project has drawn to a close. We are collecting data. The next step is to start visualizing the data and actually trying some experiments with louver positions with respect to wind and dome position. This will be a longer term effort.

The night staff have been optimizing the stacks and are now able to get stacks of less than 0.5″. The software team worked this last week to set those optimizations as the default in the stacking code.

An engineer from Austin came out this past week to begin the installation of a clean room for the much anticipated WFU corrector. This huge 4 glass Spherical Aberration corrector will be brought in from University of Arizona on a special truck that will minimize vibration. Even so, when it does arrive it will have to be tested to see if it is still in alignment. This will be done in a clean room tent we are constructing in our loading bay. This will take up the majority of the loading bay for a month and will stop us from receiving any large shipments for the dome floor. This week the frame for the tent went in.

Even over the holiday break we will continue to get some work done. The contractors working on the remote thermal area will be receiving and installing the glycol chiller on site on December 30th. The system probably will not be fully ready to go until mid-January when the 2nd VIRUS enclosure is installed.