Category Archives: HPF

This is for the HET instrument Habitable-zone Planet Finder

The week of March 31st

In the past week the HPF team from Penn State came out to remove the last components of the MRS and install the calibration enclosure for the HPF. This work went well and their enclosure is now in place. They have approved the floor paint which will go below the HPF main enclosure when they bring it out in late 2014 or early 2015.

We also made a jump forward with the mirror Strip And Wash (SAW) room. This room is connected to the mirror coating chamber and now we can do a final ZrO strip of the surface and a ultra pure water rinse and take it directly into the coating room without leaving a clean room area. This SAW room is now being used in a very manual mode and we hope to automate some components in the future.

This past week we made some small improvements in the tracker performance but we continue to have problems with the encoder. We will continue to work on this problem this week.

This week may be a little slower until we can get the problems with the tracker fixed. This will give the operations support team a chance to catch up with maintenance issues and make progress on other projects like the mirror washing room.

We also may have some contractors for Veliz Construction on site to begin the process of aluminum taping of the control building roof. This will reduce its emissivity and should help it from super-cooling at night and sending cold air into the dome. Unfortunately for Veliz the wind does not look like it will give them much of a break to actually get the work done.

The week of March 24

It has been slightly slow going with the new track electronics. We have found that some communications are flaky (bad mil-spec connections) and many of the motors require significant retuning. The PFIP test mass is in place but we want to make sure we have all motions largely tuned and reliable before we pull down the test mass and replace it with the hexapod assembly and the PFIP frame.

We have had several pieces of bad new from the University of Arizona group who are assembling the HET corrector. At the moment we have had a slip in the delivery date of three weeks and may see further slips in the near future depending upon the nature of the problems they have encountered.

Later this week the HPF team from Penn State will arrive and will be shipping out the last of the MRS and FIF components and assembling the calibration enclosure for the HPF.

The week of Feb 17

Last week week we finished clearing out the optics tables and floor for the MRS decommissioning. We also met with the HZPF team to discuss their preliminary plan for their new enclosure in the spectrograph room. Much of the staff were preoccupied with finishing preparation for the tracker lift. The crane arrived late on Friday afternoon (3 days early).

This week the Crane Services will setup for their work on Monday and will take out the lower and upper X rails that were used for shipping. We are now done with them (since the lower and upper X components are assembled and working on the telescope). On Tuesday the tracker should arrive from Austin in the morning and if the weather cooperates Crane Services will lift it into place. We expect that this will take much of the day. We hope it does not take longer because the winds are predicted to rise on Wednesday and peak at “Destructive Winds” on Thursday. Once the tracker bridge is in place we will begin cabling it and start testing moves over the next weeks.