Category Archives: WFU

Wide Field Upgrade is the commissioning effort to prepare for the new improved HET with the new secondary and instrument suite.

Week of April 2nd

The next few days are going to be very busy at the HET. The HET team along with help from Austin will be installing IFU’s for the second virus enclosure in preparation for more virus units to be installed. This involves stringing fiber cables from the enclosure up to the top of the tracker to be attached to the IHMP (Input Head Mounting Plate). The team will also be investigating and trying to remedy problems with the IHMP dither mechanism. During this time there will be no science or engineering related night work due to immobility of tracker, structure or dome for the IFU deployment.

The week of February 13

Despite some pretty poor weather this past week we are finished with the bright time engineering run and ready to start science over the 14 days around new moon. In this past engineering run we found some problems with the wave-front sensor software and implemented a new forward model of the hexapod motion. This new model allows for us to compensate for an unintended very small rotation that is induced by hexapod motion over the course of a trajectory. The impact of this rotation was to cause the field to rotate by several arcseconds over a trajectory. Our new forward model eliminates all of the hexapod induced rotation but allowed us to see a much smaller Azimuth dependent rotation term. This much smaller term will be addressed after this next science run, during the next full moon. Overall, a good improvement to the telescope’s operation.

Week of December 19th

This week has been an exciting week ramping up to science.  The Board of Visitor Staff Excellence Award Winners were announced by Director Armandroff and are as follows: Henry Cantu, Angela Davis, Steve Odewahn, and Trent Peterson.  Congratulations to the winners.

We are quickly moving in to science mode with the upcoming new moon.  Currently this week the first half of each night is being used primarily for science with the second half used for engineering due to the moon.  The weather looks to be clearing over the holiday weekend, so hopefully we will be able to collect some good data for the HET community!

The week of December 12

This week we are firmly back in our 2 weeks of engineering time. The big news is that we were able to get the wave-front sensors to properly operate in closed loop mode. This means that we are able to optimize our image quality during a trajectory small tweaks to the overall tip and tilt of the corrector above the primary mirror.

The mirror teams has kept up their rapid pace of pulling mirrors out of the array and putting in recoated mirrors. The current swap rate is 1.67 segments per week with 69 segments having been swapped since 29 February.

Week of September 19th

Big Thunderstorm

One of the many powerful thunderstorms that passed by us this month. This one produced hail just north of the HET.

This week we finally had a break in the stormy weather and started wave front sensor commissioning.  A team from Austin came out and installed an imager and wave front sensor in the IHMP (Input Head Mounting Plate) to calibrate all other wave front sensors on the telescope.  These devices once calibrated will help keep the tracker in perfect alignment with the mirror to optimize the observations we are taking for science.  This will be the main focus for the next month.  Hopefully the weather is more cooperative than it has been.  If you would like to see a time-lapse of some of the recent storms follow this link: https://www.youtube.com/watch?v=shRD2WmPWd4

The week of August 15th

Virus and Controllers

16 Virus units and their controllers lined up in the HET receiving bay. The controllers are the small boxes near the center of the image.

This week has been a busy one for the virus units at the HET.  All of the virus units were removed from the enclosure, backfilled, pumped to vacuum and reinstalled.  While doing this cooling fans were installed on all of the virus controllers to help keep the electronics cool.  They hope that this will make the virus system a bit more stable.

The HET has been churning out lots of science during dark time this month as well.  All groups that have submitted targets have received data!

The week of July 11

Last week we reported on a incident with the HET tracker that put us in a hard skew condition and shut us down. We had recovered from that skew condition but the software issues that led to the skew had continued. This week I am happy to report that we have not only installed additional skew sensors but we have found the source of the software issues. The software teams in Austin and West Texas were able to perform a series of experiments which allowed them to isolate the problem as coming from the ethernet card inside the dSpace box. This is a very specialized ethernet card but thankfully we were able to swap out a different card for it and found that all of our TCS communications problems, hexapod faults, and loading trajectory errors have gone away. We will look into getting a spare card and send the card in to see what kind of fault occurred in the card.

With the improved tracker performance we were able to start our early science operations. We took our first science targets on the night of the 16th. Unfortunately, we are now headed towards full moon which is not the ideal time to do science targets with LRS2. However, it does give us a chance to work out any inefficiencies in our PI interface, night operations interfaces and queue tools so that we can be fully ready once we get some dark time a few days after full moon.

The week of July 4th

Two weeks ago we had a fairly serious tracker issue. While recovering from a fairly typical tracker failure, the telescope operator requested that the breaks be set but instead the tracker moved in X and generated a hard skew. This hard skew actually caused the bearing to come out of the bearing block. This occurred the day that the blogger and most of the chief engineers were going to their summer conferences. Upon the return the engineers were able to determine that no permanent damage was done to the bearings or the tracker in general. The engineering team was able to move the tracker back into the block using the tracker motors. Unfortunately, the software issues that led to the skew are still present and have not yet been sorted out. This has severely limited our ability to run trajectories for engineering or the start of early science operations.

In the mean time work continues on VIRUS enclosure 2 and with re-coating of the primary mirror segments.

The week of April 18

We are currently in bright time (near full moon) and the currently active instruments, LRS2 and VIRUS are really designed to operate in dark time (when the moon is below the horizon), thus we spent this week analyzing the data taken in the last dark run, testing and updating the telescope control software and training the night time staff to make sure all of the staff have the same skills and knowledge of the system for the upcoming dark run.

One of the problems we were having in the last dark run was a mysterious end of track due to a hexapod hitting the software limit. Further investigation has revealed that this limit is part of the natural extension of the warming tracker. As the steel structure expands from warmer temperatures we have to move the hexapods down to compensate. We also found that we had set the software limits fairly far from the limit switches so we could give ourselves plenty more room without any changes to the hardware of the telescope. This is an example of the type of tuning that we continue to have to do with the control algorithms.

Both the LRS and the VIRUS are IFU (Integral Field Unit) spectrographs, which means that one could take the spectra for each fiber and reconstruct an image of the field which was observed. Below is the very first reconstruction that we did for a VIRUS field. It was a fairly bright (8th mag) standard star. The image scale is set very wide so that we can see all of the interesting features that come from the unusual design of the HET. The six image spikes comes from the edges of the hexagonal HET segments, and the stronger spikes along the X direction come from the tracker Y superstructure.

First reconstructed IFU image from VIRUS.  A very bright 8th mag standard star with the stretch set very wide to show all features.

First reconstructed IFU image from VIRUS. A very bright 8th mag standard star with the stretch set very wide to show all features.

Not long after generating this the software team was able to reconstruct a number of images for each IFU in a pointing of a globular cluster, NGC5272. Below I show a couple of examples of these.

IFU 94 on NGC5272

IFU 94 on NGC5272

IFU 95 for NGC5272

IFU 95 for NGC5272

Here is a schematic of what the current array of IFUs would look like compared to a Digitized Sky Survey Image of the field we pointed at. This is a by-product of our current setup software.

Image made by our setup software to help the astronomer understand where we are pointed.

Image made by our setup software to help the astronomer understand where we are pointed.